๐จ๐จ๐จ๐จ๐จ๐จ this was plastered by the last company and wee ripped it out ๐จ๐จ๐จ๐จ
Another bathroom transformation completed by the team here at SK Plumbing & Installations ๐ง๐ฟ
This one was certainly a challenge! The previous tradesman had clearly left the job in a terrible state and, from the work that had been carried out, it was clear he had no clue what he was doing.
The customer was understandably very unhappy and wanted us to come in, properly assess the situation and advise on the best way forward. There had been attempts to cover up damp and mould rather than deal with the underlying problems, leaving the customer with a huge mess.
We decided the only way to do the job properly was to strip everything back. The walls were taken back to brick and all the flooring was lifted so we could get everything level and start again properly.
Last guy had this for 6 weeks and never got much done, and in the Space of 8 days WOW๐
We also got to do a first fix and renew all the pipe work, the next task on this job is the kitchen next.๐
The walls were then strapped and sheeted ready for the new tile-effect wet wall.
We supplied and fitted:
๐น Tile-effect wet wall
๐น Ceiling panels
๐น New toilet
๐น Vanity unit, basin & tap
๐น New LVT flooring
๐น New macerator
๐น Toilet, basin & shower cubicle relocated
๐น Floors lifted and levelled
๐น Walls stripped back, strapped and sheeted
๐นnew LED mirror
๐นnew spot lights also
A massive amount of work went into turning this bathroom around, but the end result speaks for itself.
The customer was absolutely over the moon with the finished bathroom, and thatโs what matters to us โ doing the job properly and leaving the customer with a result they can be proud of. ๐
PS THE MACERATOR WILL BE CONNECT UP SOON, THE CUSTOMER WANTED THE WASTE RUN ALONG THE FRONT OF THE WALL INCASE ANYTHING HAPPENS IN FUTURE.
FEW TRIMS STILL TO BE DONE BUT WHAT A PROJECT THIS WAS