03/05/2021
Hey all, it’s been a while. Work on completing the cottage has been going on but not a lot of it is noticeable with a picture, snagging list is growing but also being ticked off.
The bedroom in the side extension is now complete, the electrical second fix in the downstairs part of the side extension has also been finished. Once the finished flooring has been laid in that area, the cloakroom, boot room, office and laundry areas can all be completed.
The one noticeable change is outside. The retaining walls which form the courtyard and raised beds have been rendered. What a transformation, no more looking at concrete blocks. Once painted we can then look to get the area slabbed.
#