11/09/2026
*NEW PROJECT UPDATE* 🏗️
We've been working on this stunning property for the past few weeks, with alterations now well underway.
This retaining wall was completed last week. The old single-skin wall had finally given way, so down it came along with the old footings.
After digging the bank back and digging new foundations, we poured the concrete with multiple steps due to the slope of the hill. The new wall was built with concrete blocks laid flat for extra strength and finished with a monocouche coloured render by Lewis Faulkner at LPF Plastering Services. 👏
A solid, long-lasting solution with a premium finish.
Watch this space for more updates on the alterations to come.