Renovation update
The structural transformation is now well underway, and the difference is already huge!
The new structural steelwork is now in place, opening up the existing layout and creating one large, open-plan space.
We’ve also:;
•Formed a new doorway from the hallway
•Blocked up the existing doorway
•Broken out the brickwork beneath the existing windows ready for the new bi-fold doors
•Continued with the first-fix electrical and plumbing works
We’re now finishing off the first fix before our pre-plaster inspection. Once that’s signed off, we’ll be closing everything up and getting the walls and ceilings plastered, ready for the new kitchen installation.
A lot of work happening behind the scenes, but the finished space is really starting to take shape now!
Next stage: plastering and getting ready for the kitchen…