08/11/2023
🗓️ Revisiting a project that we completed a couple weeks ago, doing all the approach works for the new Willow Bridge, replacing Pontoon Bridge at Nene Park.
👷🏻♂️ On both sides of the bridge, we dug out, installed steel reinforcing and concreted 6 pad foundations, 1 for the ballast wall to sit on and 5 for the fencing to sit on. We also built up the pathway with a layer of 225mm Type 1, timber spline edgings and 85mm of Tarmac. Finishing off by importing fresh topsoil and grading it down to the existing levels.
✅ Excellent work from our team, even with challenging weather conditions towards the backend of the project.