🔨 Project Update | Reactive Platform Repairs | Cholsey Station
MLG UK Ltd carried out reactive platform repairs at Cholsey Station following the discovery of significant deterioration to the steel supports beneath Platform 2.
Working alongside Network Rail, GWR and the planning teams, our team developed a practical solution, installing 1,500 sandbags over four consecutive nights to provide temporary support and help protect the platform.
The works required careful planning and rapid mobilisation, with restricted access and railway operations adding to the challenge.