06/06/2026
We had a hectic fortnight squeezing in this supply & fit project for a new restaurant upstairs in Thompsons Nightclub building, Belfast. This was our 3rd & final phase of work in this building over the past couple of years.
This job had a strict deadline which need met, working along side M&E on site.
- The pitched ceilings received an MF system, rockwool slab above, 50mm kingspan & wallboard below.
- Exterior liners received 2x2 timber, 50mm kingspan between, a layer of VCL and plasterbaord to face.
- Internal partitions built with 90mm stud, rockwool slabs and 18mm plywood Patressing internal with wallboard finish.
- Staircase from GF- 1st got gypliner system with MF ceiling for the new entrance.
- 2 new Fire escape routes built.
- New Unisex toilets built, with MF ceilings to
Complete the fitout.
All our plasterboard received a T&J finish, ready for the painter.
All the best to Aughrim Build and the owners of Thompsons as the finishing fitout now starts.
🤝 ✅