13/10/2026
Chalfont Project | Progress Update 🧱
Good progress on our Chalfont project, where we’re constructing a new extension to create additional living space.
Starting with the groundworks, we’ve excavated and poured the foundations, installed new underground drainage and inspection chambers, built up the substructure and prepared the floor with insulation and a concrete slab.
The cavity walls are now progressing well, with brickwork to match the existing property and insulation being installed as we build.
Plenty of work goes into a project before the roof goes on, and these photos show just how much is involved in getting everything to this stage.
More updates to follow as the build progresses.
ZINK Construction Ltd | Norfolk