Wilson + Hereward is officially taking shape!
Framing is now underway, with crews working through the floor systems and prefab wall installations. With the crane lifting wall panels into place, this is one of those stages where progress becomes especially visible.
Foundation and concrete work are complete, along with major underground drainage, damp proofing, and backfilling. The focus has now shifted upward as engineered floor systems and prefab wall packages are installed level by level.
Behind the scenes, our team continues to coordinate structural details, trades, inspections, and material deliveries to keep the site moving efficiently.
Next up, we’ll continue framing the upper levels, bring in the crane for the remaining wall packages, and move into roof trusses once the upper floor framing is complete.