600 amps. 12,000 pounds. One serious installation. 💪
We’re fortunate to work with clients who bring us some pretty unique challenges.
On this Forest Hill project, we were asked to install a 600-amp power vault for a new residence to accommodate the Toronto Hydro electrical service.
Our team got to work excavating the base with our Kubota Canada U35 excavator from Kooy Brothers Len Janse preparing the foundation with a minimum of six inches of clear gravel, and carefully leveling the base before assembling the three-piece precast vault.
A big shoutout to JCL Concrete Pumping for keeping the gravel supply moving with their gravel slinger, making it possible to efficiently place the clear gravel exactly where we needed it.
Then came the big part…
We brought in our Freightliner truck equipped with a Hiab crane to set the vault into place. The second section weighed approximately 12,000 pounds, pushing the limits of our crane’s lifting capacity. We had to carefully plan and build an entranceway to get the truck and crane into position.
With great coordination between our team and the electrician, we got everything installed, perfectly level, and ready for the Toronto Hydro inspection.
The best part? We’ve incorporated the vault into the overall landscape design so it will be beautifully concealed from view once the project is complete.
These are the challenges we love.
At Parkscape, we don’t say no when our clients bring us something unique. We figure it out, bring the right people and equipment together, and get the job done.
This is what sets us apart.