Progress continues at DENT Cabbagetown as the project moves deeper into the finishing stages. 🏗️🦷
This week, several key milestones were reached:
✔ Ground floor HVAC ductwork is now approximately 90% complete
✔ Second-floor plaster work has been completed
✔ Ground-floor plaster work is approximately 50% complete
✔ Electrical service preparation is finished and the project is now awaiting Toronto Hydro connections
One of the most rewarding parts of a renovation like this is seeing the transformation from exposed framing and mechanical systems to finished spaces that begin to reflect the final vision. The natural light coming through the future treatment and clinical areas is already giving a glimpse of what's to come.
We're excited to continue bringing this new clinic to life for Dr. JB Spillane and the team at DENT Toronto.
Follow along as we continue to transform this historic Cabbagetown building into a modern dental practice.