08/19/2026
It’s been a busy few weeks!
McTavish Street project- slabs were poured, exterior walls were framed and wrapped. Tomorrow we start framing the roof! 🔨
Aiden Street project- foundation was poured, backfilled, underground plumbing roughed in and is ready to receive the concrete slabs. 🔨
Howe Crescent project- excavation has started and is on going. 14’ to get down to undisturbed soil. A 20 ton excavator feeding a 35 ton 😲
Yoho Lake project - the funky little 1 bedroom cottage style home is close to the finish line🔨
All this going on and we got away from work for a few days for some well deserved family time 😃
It’s great to be busy 🔨👊