Carver Construction

Carver Construction Carver Construction was established in 2009 and is based in Kelowna, BC. Carver focuses on water and wastewater projects throughout Western Canada.

Since our inception in 2009 Carver Construction Ltd. has provided General Contracting , Design-Build and Construction Management Services to a wide variety of Private and Public-Sector clients.

Civil works is underway on one of our newest projects up in Taylor BC.  Construction for a new Wastewater Treatment Plan...
06/03/2025

Civil works is underway on one of our newest projects up in Taylor BC. Construction for a new Wastewater Treatment Plant Solids Dewatering facility will consist of a screw pile-supported masonry block building that will house a new dewatering centrifuge and all related appurtenances complete with tie-ins to existing infrastructure including an overbuild manhole and tie-in to an existing sludge holding tank.

Carver was selected as the Preferred Proponent to construct the replacement reservoir for the City of Enderby in Novembe...
05/22/2025

Carver was selected as the Preferred Proponent to construct the replacement reservoir for the City of Enderby in November 2024. We worked with the Client and Engineer over the winter months to bring the reservoir within the city’s budget. The project team consisting of ourselves, the consulting engineer and local subcontractors collaborated extensively to come up with cost saving ideas through alternative materials and revised project designs to arrive at a credit value acceptable to the Client and allow the project to proceed.
Demolition of the existing reservoir started in March and the base slab for the new reservoir was completed at the beginning of this month (May).

Here is the Carver team that participated in the Wilson M Wilson M. Beck Insurance (Kelowna) Charity Golf Tournament in ...
09/17/2024

Here is the Carver team that participated in the Wilson M Wilson M. Beck Insurance (Kelowna) Charity Golf Tournament in July. 🏌️⛳️

All proceeds raised at the WMB tournament go towards funding the YMCA’s financial assistance program. These funds ensure the growing number of local low income families can access Y programs focused on child care, water safety, mental health supports, sports, camps, and recreation, that they couldn’t afford otherwise.
Thank you for choosing our cause, supporting low income individuals, and putting on such a fun and high impact tournament!

Carver is proud to be a Silver Sponsor for this event.

A few weeks back a fun time was had by all that could go, when we tried out the (fairly) new indoor go-karts at Kelowna ...
09/17/2024

A few weeks back a fun time was had by all that could go, when we tried out the (fairly) new indoor go-karts at Kelowna Karting.

What a blast!!
We all recommend giving it a go!

Update on the Larkin Reservoir in Spallumcheen:The rock has been removed and we have poured the base slab for the reserv...
09/06/2024

Update on the Larkin Reservoir in Spallumcheen:
The rock has been removed and we have poured the base slab for the reservoir.

This month Carver mobilized to site in Spallumcheen after being chosen as the Preferred Proponent to construct the Larki...
06/27/2024

This month Carver mobilized to site in Spallumcheen after being chosen as the Preferred Proponent to construct the Larkin Reservoir for the Township. We are excited to work with Urban Systems again and provide the Township of Spallumcheen with a new reservoir.

Carver was awarded Pretty Road Improvements in Lake Country through the RFP process.  We kicked off the job back in Marc...
06/27/2024

Carver was awarded Pretty Road Improvements in Lake Country through the RFP process. We kicked off the job back in March and look forward to having a successful project with the District and WSP.

Big concrete pour yesterday (250 cu.m.) up at the reservoir for Big White Ski Resort Ltd.Base slab completed! Way to go ...
08/02/2023

Big concrete pour yesterday (250 cu.m.) up at the reservoir for Big White Ski Resort Ltd.
Base slab completed! Way to go everyone!

Here is a local article about the new reservoir we are tackling up at the Ski Resort here in Kelowna.
07/27/2023

Here is a local article about the new reservoir we are tackling up at the Ski Resort here in Kelowna.

Construction of a new water reservoir is taking shape at Big White Mountain Resort.

Started construction on the new reservoir up at Big White Resort at the site beside the existing.  Carver is excited to ...
07/26/2023

Started construction on the new reservoir up at Big White Resort at the site beside the existing.
Carver is excited to be working alongside Big White Utilities and Ecora Engineering.

Been a busy month in Keremeos installing equipment!
05/31/2023

Been a busy month in Keremeos installing equipment!

Address

Kelowna, BC
V1V2W5

Opening Hours

Monday 8am - 5pm
Tuesday 8am - 5pm
Wednesday 8am - 5pm
Thursday 8am - 5pm
Friday 8am - 5pm

Alerts

Be the first to know and let us send you an email when Carver Construction posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Carver Construction:

Share