06/15/2026
Strong progress continues at our 54-Unit project in Dieppe.
Siding installation is progressing steadily, while curbs, sidewalks, paving and landscaping are next up to complete the project exterior. π§
On the interior, painting, finish work and flooring are all ongoing as the building continues moving closer toward final completion.
π’ 54-Unit Apartment
π230 Amirault St, Dieppe NB