ποΈ Comfort Residence β Malinova Dolina 2: Construction Progress Update!
Find out more here: https://stonehardpremier.com/market-news/napredk-v-stroitelstvoto-na-comfort-residence-malinova-dolina-ii-za-mesec-septemvri-2026-g
The scaffolding has now been removed, revealing the faΓ§ade of the residential building, while construction continues according to schedule, with completion planned for the end of 2026.
The following construction works were completed over the past month:
β’ The metal cladding of the entrance canopy has been completed;
β’ Porcelain stoneware tiles have been installed on the terraces;
β’ Gypsum plastering has been completed on the fourth residential floor and in the staircase;
β’ Measurements have been taken for the entrance doors;
β’ The scaffolding has been dismantled.
The following works are planned for the coming month:
β’ Installation of the entrance doors;
β’ Installation of the elevators;
β’ Laying of polished concrete flooring in the underground garages;
β’ Completion of the granite finishes in the common areas;
β’ Commencement of the landscaping and external site works;
β’ Completion of the installation of the external terrace railings.