Alright guys, this is as good as our weekly wrap-up is going to get 🤣 blame our socials girl for leaving us unattended.
Massive week for the boys in Lismore getting stuck into Stage 1 of the Lismore Courthouse infrastructure upgrade for the NSW Government.
We’ve landed the 220kVA generator and 5,500-litre fuel cell, pulled in all the 150mm² XLPE incoming supply, completed all the cable tray works, plus all the generator power, lighting and controls.
Everything’s tested, commissioned and ready for the outage next week.
Massive effort from the boys getting all that smashed out in only four days.
And special shoutout to Jackson for thinking he could outdrink me on the red w**e last night…
Better luck next time, mate. 😂🍷
That’s a wrap from Lismore. See you next week!