22/06/2026
Council Stormwater Rehabilitation Completed ✅ 🚧
This project involved the replacement of a deteriorated 300mm reinforced concrete stormwater pipe connected into existing pit infrastructure, with works completed in a live service corridor containing multiple nearby utilities.
The team carried out controlled excavation around existing gas, water and telecommunications services to safely expose the damaged stormwater asset without service strikes or disruption.
Works included:
• Dial Before You Dig checks
• Site briefing and safety controls
• Careful excavation around existing services
• Removal of deteriorated 300mm stormwater pipe
• Installation of new 300mm reinforced concrete pipe
• Connection into existing pit infrastructure
• Pit sparging and benching to improve flow
• Backfill, compaction, reinstatement and clean-up
A clean and professional result for a council stormwater asset, with the pipe replaced, hydraulic flow improved and the area reinstated on completion.
For council, civil, excavation, stormwater drainage and asset maintenance works, get in touch with Oz Excavations and Plant Hire.
Excavation