🚜 42 CUBIC METRES OF CONCRETE… AND ONE VERY EARLY START! 💪
What a transformation at Lillydale Lake!
From the first bucket of dirt to a beautifully finished concrete slab, the new Multi-Sport Court Play Area is really taking shape!
⏰ 5:30am start for the Scratchin the Surface team, getting everything ready for the big pour.
đź’Ş 42 cubic metres of concrete, pumped, screeded and finished - and just look at that result!
And we have to say… we’re still loving those curves! 👌
Next up, the concrete will be cut on Monday, followed by a 28-day curing period before the acrylic sports coating is applied.
There’s a lot of work that goes into creating a quality sporting surface, and it’s pretty satisfying seeing all that preparation come together.
Another great local community project we’re proud to be part of.