12/02/2026
Some jobs are not about speed
They are about getting it right
This one took close to 16 weeks from initial contact to ex*****on
An existing switchboard that simply did not have the capacity to support an additional shop
No spare space
No easy workaround
No shortcuts available
So the solution was a full rethink
Redesigning the chamber
Coordinating with AusNet
Working alongside Aston Construction
And executing the changeover on a Sunday to minimise disruption
This is the part most people never see
The planning
The approvals
The redesign
The coordination
And the hours spent making sure when power goes back on everything is safe compliant and future ready
We help businesses reduce risk stay compliant and avoid downtime through smart electrical data and security systems.
Powered connected and secured.
Big thanks to everyone involved for backing the process and trusting the long game