30/05/2026
Replacement of a failed site main switchboard, failed 240mm2 XLPE consumer mains and two further distribution boards which were also fed by 240mm2 orange circular 4c+e cabling which had suffered burn out at RGR Road Transports very busy depot here in Port Hedland. We had to implement temporary generators to keep the wheels rolling. A big effort from the team to get this over the line and thanks to the customer for being patient whilst awaiting custom switchboards to be built.