Now that the concrete paving is down, the Alfresco – outdoor cabinets can be installed Once the cabinets are installed, ...
03/07/2020

Now that the concrete paving is down, the Alfresco – outdoor cabinets can be installed
Once the cabinets are installed, the tiler can come back and complete the tiling above the bench

The grano is poured and tape is put across the entry to stop people driving on it and a dropsheet to cover it while the ...
02/07/2020

The grano is poured and tape is put across the entry to stop people driving on it and a dropsheet to cover it while the painter does the garage ceiling/
The paved (or in this case, concreted) areas are prepped ready for the concrete to be delivered.
The Part B pest control is put down just before the concrete is ready to be poured, As it is such a large area, it had to be done on 2 separate days as the concrete goes right around the back of the house.

Once the tiling is finished, the shower screens, mirrors and sliding doors can be measured.The painter starts, and depen...
30/06/2020

Once the tiling is finished, the shower screens, mirrors and sliding doors can be measured.
The painter starts, and dependent on the weather, he may start outside..
The grano hardstand (garage floor) prep and site clean is done, ready to be poured.
Once the grano is down, the garage door can be measured.
Before the painter starts painting he will put dropsheets around to protect the surfaces, If he is painting the walls he may even put plastic over the windows

The tiling will take several days sometimes up to a couple of weeks, it is manual labour and each tile has to be laid in...
29/06/2020

The tiling will take several days sometimes up to a couple of weeks, it is manual labour and each tile has to be laid individually and tiles will have to be cut to fit one at a time.
Here our client wanted to have a feature wall of ceramic tiles flowing from outside to inside as the front entry door is a glazed door, they can be seen from both inside and outside.
Our clients requested full height tiling to all the bathrooms. When we install full height tiling, it is laid to the underside of the cornice.

The tiler comes in and does the screeds to the wet area floors. He will need clean sand and bricks for any hobs and unde...
28/06/2020

The tiler comes in and does the screeds to the wet area floors. He will need clean sand and bricks for any hobs and underneath an wet area cabinets.
Once the screeds are dry, the waterproofer comes and paints the waterproof membrane in the shower recesses.
The waterproofing has takes a couple of days to dry and then the tiler can come back and start laying the tiles.

27/6/20The stone tops are installed, the sinks, troughs and basins are all fitted and final adjustments to any doors and...
27/06/2020

27/6/20
The stone tops are installed, the sinks, troughs and basins are all fitted and final adjustments to any doors and drawers are made.
The rangehood and any strip lighting in or under the cabinets is installed.
The ceiling contractors come back and install any missing cornice.

Sometimes, due to the amount of cabinets in the home, it will take several trips for installation.Even though this is a ...
26/06/2020

Sometimes, due to the amount of cabinets in the home, it will take several trips for installation.
Even though this is a smaller home on a rear strata block, the cabinetwork in the home is extensive, so several trips were needed.
The handles are installed covered with plastic to help stop them getting scratched.
Drawer units and doors are fitted and when they are all on, the cabinetmaker may need to adjust the hinges or rollers, to ensure they are all aligned correctly.
it’s now starting to come together, it looks very stark at the moment as there are no contrasting tops or splashbacks in yet, once they go in, it will make a massive difference.

The electrician will come and pull through the wires ready for the lights and power points, they may even cut holes in t...
23/06/2020

The electrician will come and pull through the wires ready for the lights and power points, they may even cut holes in the ceilings for the exhaust fans.
The cabinets are installed. Generally when there are stone tops, the carcasses, doors and panels are fitted and the stone tops are fitted at a later date.
When there are cabinets that go to the ceiling, the cornice will need to be fitted afterwards, so the ceiling contractors will come back to site and fit the lengths they weren’t able to fit before.

The fixing carpenter fits all the shelving, hanging rails and doors, he will drill the holes for the door handles, and h...
22/06/2020

The fixing carpenter fits all the shelving, hanging rails and doors, he will drill the holes for the door handles, and he will install the front and garage door entry internal only, the remainder aren’t fitted until after the doors have been painted.
Our clients chose a push button deadlock for their home, and there is no handle. The towel rails and toilet roll holders are fitted after the home has been painted, and the fixer will come back and fit the remaining items.

Now that the house is locked up, the exciting stuff happens.Unfortunately you won’t be able to see a lot of it.The cabin...
21/06/2020

Now that the house is locked up, the exciting stuff happens.
Unfortunately you won’t be able to see a lot of it.
The cabinetmakers will come and do a site measure once the walls are set and the ceilings are complete.
When there are overhead cupboards, the cabinetmaker needs to check the bulkheads are straight and take measurements rather than rely on dimensions on the plans.
Have you ever wondered why there are bits missing on the white set on the walls.
They don’t put white set where there are cabinets or tiling, however, in this house, the clients wanted glass splashback, so the white set is put behind the glass.

Once the ceilings are in, the glazing is installed in the windows. Having the glazing in before the white set helps to s...
20/06/2020

Once the ceilings are in, the glazing is installed in the windows. Having the glazing in before the white set helps to stop it drying out too quickly. The white set and any external render is put on ready for painting.
The doors and fixing hardware is delivered and the house is locked up.

Now that the roof is covered, the plasterers come in and put the grey float on the walls.Once the float is done, the cei...
19/06/2020

Now that the roof is covered, the plasterers come in and put the grey float on the walls.
Once the float is done, the ceiling contractors come in and put the ceiling and any plasterboard wall linings on.
The boards are “thrown”, fixed to the steel battens or wall plates, they are then flushed, and the cornice installed, once they are all dry, the contractors will come back to site and sand all the joins.

The roof sheets, gutters, flashings, flumes and anticon are delivered to site and the roof plumber can install the roof ...
18/06/2020

The roof sheets, gutters, flashings, flumes and anticon are delivered to site and the roof plumber can install the roof cover.
In this instance there was a BAL level 12.5 (Bushfire attack level) .on the house, so anticon had to be placed under the roof sheeting to the entire roof area.
And as the house is built in a built up area with mature trees, we installed gutter guard to keep the leaves and branches from filling the gutters.

The roof trusses are delivered and the roof framers build the roof structure install the fascia and line the garage and ...
19/05/2020

The roof trusses are delivered and the roof framers build the roof structure install the fascia and line the garage and any eaves linings. The roof is tied down to the brick work with roof hold down straps
Once the roof frame is built, they install the roof battens, these are lengths of steel that the roof sheeting is screwed to.
When the battens have been installed, we call for a roof measure. The roof plumber will do a site measure for the roof sheets, gutters, downpipes and any external flumes.

The roof trusses are delivered and the roof framers build the roof structure install the fascia and line the garage and ...
16/05/2020

The roof trusses are delivered and the roof framers build the roof structure install the fascia and line the garage and any eaves linings. The roof is tied down to the brick work with roof hold down straps
Once the roof frame is built, they install the roof battens, these are lengths of steel that the roof sheeting is screwed to.
When the battens have been installed, we call for a roof measure. The roof plumber will do a site measure for the roof sheets, gutters, downpipes and any external flumes.

The aluminium doors and windows are covered with protective plastic so Brickwork is nearly complete, the door, window fr...
14/05/2020

The aluminium doors and windows are covered with protective plastic so Brickwork is nearly complete, the door, window frames and roof hold down straps have been installed.
As the house is a rear strata home, the meter boxes are installed in a pier on the boundary
We now need to organise a crane to lift the TBar above the garage and above the alfresco brickwork.
The roof frame is called up, and the trusses are built in the factory ready to be delivered to site.

The brickies have erected their profiles and brickwork is well underway, the brickies kit (scaffold) has been delivered ...
23/04/2020

The brickies have erected their profiles and brickwork is well underway, the brickies kit (scaffold) has been delivered to site so the brickies can lay the higher bricks.
The unsupported brickwork is propped at the end of each day so that it doesn’t fall.
Weather can make a huge difference in the time taken to complete the brickwork, the brickies are working outside in the weather, and in this case it was during the hot summer days.
As there are time restrictions, they can only start work at the time each shire has nominated and will work through the day, but knock off early afternoon. On extremely hot days, and when there is a string of them, the trades may not be on site due to the heat.

Once all trades have been to site and laid the services in the trench, they are backfilled and compacted. Unfortunately ...
21/04/2020

Once all trades have been to site and laid the services in the trench, they are backfilled and compacted.
Unfortunately on a rear strata lot, there isn’t room to spread the excess soil so it will need to be removed from site.
When the excess soil is removed and the slab cleaned, the brickie can come to site and string out for the brickwork.
Now the slab is clean, and the brickie has strung out, we organise to have the bricks delivered and loaded, brick hardware, door frames, window frames, lintels, shed and cement delivered for the brickies to start work.

As the block is a rear strata lot and the sewer is in the rear of the lot, it needs a single concrete pile to protect th...
18/04/2020

As the block is a rear strata lot and the sewer is in the rear of the lot, it needs a single concrete pile to protect the house from subsidence if the Water Corporation have to come and do any works on the mains.
When the footings are poured, the concrete pile is poured at the same time.
Before the slab pour, the grano books the concrete pump and the concrete to come to site as early as possible.
Concrete goes off by a chemical reaction, but still can be affected by the heat, wind which will dry the surface and create crazing, so he will want to get the concrete in place as early as possible to allow as much working time as possible.
On extremely hot days, we also allow to spray the slab with a curing compound which retains the moisture in the slab and slows the curing time, this helps lessen the chance of shrinkage and cracking to the slab.

Once the footings have been poured the slab is generally booked for the next day, before the concrete pump and concrete ...
14/04/2020

Once the footings have been poured the slab is generally booked for the next day, before the concrete pump and concrete truck arrive on site, the grano prepares for the pouring of the slab by installing his form boards.
These boards hold the concrete in place as its poured.
The plumber will generally put foam blocks around the waste pipes for toilet suites to make it easier to install them and the pipes are generally capped or taped closed to stop building rubble falling in.
Steel rods are placed in the slab by the concretor as the concrete is pumped in and the bar chairs are in place to lift the mesh off the plastic.

As this is a rear strata home, a concrete pump is used to pump the concrete from the front of the property to the rear l...
09/04/2020

As this is a rear strata home, a concrete pump is used to pump the concrete from the front of the property to the rear lot.
Once the footings have been dug and the plumbing prelay is complete, the concrete and concrete pump are booked.

After the earthworks are done, the block is re pegged by the surveyor, to ensure the pegs are in the correct place befor...
02/04/2020

After the earthworks are done, the block is re pegged by the surveyor, to ensure the pegs are in the correct place before laying the ground slab.
The grano workers use the pegs to get correct dimensions for the setout of the footings and slab.
The plumbers come in and do the plumbing prelay for the slab.
They dig the trenches for all the wastes and water lines that go under the slab
The grano worker strings out the area of the slab, and digs the footings, the pest control company comes in and does a termite prelay spray, called a Part A, the grano then lays black poly, bar chairs and mesh over the slab area before the concrete footings are laid.

Our clients engaged us to build a rear strata, lock and leave home, and have given us permission to document and share t...
26/03/2020

Our clients engaged us to build a rear strata, lock and leave home, and have given us permission to document and share the progress of their new home.
Over the next weeks we will share the progress of their home.
As it was a rear strata property of only 313m², to be able to fit the house on the block there had to be 2 parapet (online boundary) walls and piling to the footings as the lot had a sewer easement due to the proximity of the sewer line.
Building boundary walls means, before we could start any works on site, the neighbouring fences had to be removed and neighbours consulted.
These photos show the clearing of the lot, fences removed and earthworks.

In the second post of this series of blog posts we will cover what is included in a build to lock up home, insurances an...
11/11/2019
Owner Building & Building To Lock Up Series – Part 2

In the second post of this series of blog posts we will cover what is included in a build to lock up home, insurances and designs and plans and answer the question, is building to lock up cheaper. What is included in a build to lockup Building to lock up is pretty much as it sounds, we build the main structure of the home including walls, roof wall and ceiling linings (unless you have requested they be omitted), external windows and doors so the home is locked up and secure. [ 556 more words ]
https://www.centralavenuehomes.com.au/owner-building-building-to-lock-up-series-part-2/

Central Avenue Homes have built custom designed homes from lock up and any stage to completion in and around Perth for over 20 years.

Continuing our look into passive design principles, we look at the importance of site orientation and how to use it in y...
04/11/2019
Site Orientation & Characteristics - Central Avenue Homes

Continuing our look into passive design principles, we look at the importance of site orientation and how to use it in your original design. Image: Passive Epringham House, MSG Architecture 2015 A clever site responsive design can reduce heating and cooling loads and the need for expensive upgrades for the comfort of your home. When working on the initial design… [ 471 more words ]
https://centralavenuehomes.com.au/site-orientation-characteristics-2/

Central Avenue Homes specialises in passive design, site orientation and custom design homes to suit all blocks to and to your budget

Group dwellings and multi-unit developments For more than 20 years, Central Avenue Homes has worked with many clients to...
01/11/2019
Unit development – Group dwellings - Central Avenue Homes

Group dwellings and multi-unit developments For more than 20 years, Central Avenue Homes has worked with many clients to design and build their multi-unit and group dwelling investment properties. We have worked on relatively simple projects from triplex duplex single storey double storey units to 5,6,7, 8 and 9 double storey townhouse developments The 9 group dwelling was recently completed in the northern suburbs. [ 413 more words ]
https://www.centralavenuehomes.com.au/multi-units-group-dwellings/

Central Avenue Homes have worked with many clients to design and construct their multi unit and group dwelling investment properties for over 20 years

What is Owner building from lock- up? Have you tried to obtain finance for Owner building your dream home and the banks ...
30/10/2019
A simplified explanation of Owner building from lock-up

What is Owner building from lock- up? Have you tried to obtain finance for Owner building your dream home and the banks won’t even consider it. We have been building to lockup for our clients for nearly 20 years. In this blog post, we explain what Owner building from lock-up is, and what services you can expect from us. Building to lock… [ 609 more words ]
https://www.centralavenuehomes.com.au/owner-building-lockup/

Central Avenue Homes have helped owner builders buil to lock-up and completion for our clients in and around Perth for over 21 years.

Planning conditions and building approvals in Western Australia are continually changing. Therefore, more suburbs are no...
21/10/2019
Bushfire Prone Areas - BAL assessments - Central Avenue Homes

Planning conditions and building approvals in Western Australia are continually changing. Therefore, more suburbs are now subject to BAL (Bushfire Attack Level) assessments. BAL (Bushfire Attack Level) As a result of bush fires around the country, the WA State Government passed a law that if you are building in a bushfire prone area, you will be need a Bushfire Attack Level (BAL) assessment. [ 509 more words ]
https://www.centralavenuehomes.com.au/bushfire-prone-areas-2/

Central Avenue Homes in house designer will work with you on your BAL (Bushfire Attack Level) assessment to keep the cost as low as possible.

Have you tried to obtain finance to Owner build your dream home and the banks won’t even consider it. In this blog post,...
29/08/2019
Can't Get Finance For Owner Building? Why Not Build To Lock Up

Have you tried to obtain finance to Owner build your dream home and the banks won’t even consider it. In this blog post, we will explain what building to lock up is, and what services you can expect from the Builder. What is building to lock up? Building to lock up is when the builder builds the main structure of the house and finishes his works, generally as soon as the house is locked up. [ 512 more words ]
https://centralavenuehomes.com.au/explaining-building-to-lock-up/

Central Avenue Homes have built custom designed homes from lock up and any stage to completion in and around Perth for over 20 years.

Considering building your own home (owner builder), but don’t have the time, confidence or knowledge, then, consider bui...
23/08/2019
Can't get finance - Build to lockup with Central Avenue Homes

Considering building your own home (owner builder), but don’t have the time, confidence or knowledge, then, consider build to lock up. Central Avenue Homes have been building to lock up for our clients’ since 2004 and to completion since 1998 in Perth and surrounding areas. Building to lock up, is not for everyone but it may suit your own situation down to the ground. [ 546 more words ]
https://www.centralavenuehomes.com.au/owner-building-building-lockup/

Central Avenue Homes have built custom designed homes from lock up and any stage to completion in and around Perth for over 20 years.

Address

Unit 1/27 Erceg Road YANGEBUP
Perth, WA
6164

Opening Hours

Monday 9am - 5pm
Tuesday 9am - 5pm
Wednesday 9am - 5pm
Thursday 9am - 5pm

Telephone

08 9456 3366

Alerts

Be the first to know and let us send you an email when Central Avenue Homes posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Central Avenue Homes:

Central Avenue Homes

At Central Avenue Homes we exist to assist our clients build the home they have dreamed of.

Greg and Lee, our husband and wife team, have gathered over 35 years of home building experience and opened our doors to offer clients a unique one-on-one experience.

Central Avenue Homes has operated since 1998 with clients continuing to entrust us with designing and building their custom homes to the highest standard. When you build with our team you will have confidence knowing a small team of experienced industry members are pouring over every detail of your home – striving for the best outcome with you in mind.