06/10/2026
At SIMPEC, we are continually striving to find more efficient ways to deliver on our projects. We aim to find efficiencies in both time and cost while maintaining safety as our highest priority.
Recently, one of our projects reached a significant milestone with the installation of the first of four pre-assembled roof trusses. The truss was successfully lifted into place using a 480-tonne crane with a 24-tonne payload.
By pre-assembling the trusses, we have been able to minimise electrical and structural work at height, reducing risk while improving safety, efficiency, and overall project delivery.
Congratulations to the team on this achievement. Three more to go!