30/01/2025
We’re excited to share the latest progress on our project at Drouin Primary School in regional Victoria!
A strong finish to 2024 saw the lift shaft completed, services roughed in, and external brickwork nearing completion.
Now back on site, our talented subcontractors are hard at work with plastering, window installation, and the distinctive feature painting of the brick facades.
This ambitious project includes a brand-new Community Hub, a double-storey Learning Hub with a competition-grade gymnasium, and a new Administration Building. Once finished, the upgraded facilities will accommodate an additional 225 students, supporting the growing Greater Gippsland community.
Follow our socials for more updates as we continue to bring this transformative project to life!