19/01/2023
ALLROADS’ Beaudesert-Nerang Road and Maudsland Road Intersection Upgrade and Safety Enhancement Works project for DTMR is nearing completion, with the project on track to wrap-up in mid-February. The team have now completed all of the major excavation works (up to 3m lowered off the previous road height) with only some minor excavation remaining.
This month has also seen the team move onto the finishing works including kerb, concrete footpaths and bus stops, landscaping, asphalt works and installation of guard rail, with the asphalt wearing course, linemarking and installation of traffic signals to follow in February.