31/08/2026
We’re getting very close at Prospect House, with approximately 5 weeks to go until completion.
A few of the final pieces are starting to come together:
✨ The LED strip lighting to the stairs is now complete
🔌 Our sparky will be back in a few weeks to finish wiring the remaining points
🌬️ The HRV system is getting its final installation and commissioning work
đźšż Bathroom grouting is about to get underway
🪵 Flooring will bring the spaces together once laid
At this stage, it’s all about those final details that take the house from a construction site to a finished home.
Not long now. Prospect House is almost there.