01/10/2026
Strong progress continues at our Elimbah East project, where Silverstrand is delivering the civil, mechanical and electrical package for the new sewer rising main, pump station and barometric loop infrastructure. The project includes approximately 5.5km of new sewer rising mains, a new sewer pump station, emergency storage facilities and associated odour control systems. 🚧
To date, four micro-tunnel bores have been successfully completed, and approximately 1,200 linear metres of dual sewer rising main installed. Restoration works are now underway across completed sections, while tunnelling and pipeline installation continue along the remaining alignment.
At the new Sewer Pump Station and Barometric Loop site, the team has completed the major concrete pours for the pump station structures, maintenance holes and associated concrete assets. Construction is now progressing on the valve chamber, flow meter pit, air valve pit and remaining maintenance hole structures.
With procurement of the major mechanical, electrical and process equipment now complete, the project is well positioned to progress into the next phase of construction and commissioning activities.
A great effort by everyone involved as we continue delivering this critical wastewater infrastructure to support growth and development within the Elimbah community.👏