PSD Energy PSD Energy is an electrical engineering construction company which focuses on the delivery of turnkey projects.

It’s raining outside the lightning masts are up, but that doesn’t stop the 220kV cable termination. 220kV cable terminat...
16/03/2026

It’s raining outside the lightning masts are up, but that doesn’t stop the 220kV cable termination. 220kV cable terminations are an art of its own.

Looks like nothing to most but means allot to us. Great job 220kV installed and clamped ready for termination
25/02/2026

Looks like nothing to most but means allot to us. Great job 220kV installed and clamped ready for termination

Amazing effort by an amazing team   you can’t get better than this. Solar nearly done and BESS progressing well.
07/02/2026

Amazing effort by an amazing team you can’t get better than this. Solar nearly done and BESS progressing well.

31/01/2026
31/01/2026

21st year it’s amazing how quickly 20 years fly by.

27/01/2026

Solar and BESS and all the hi tech engineering that goes with it. Most see a white box and black glass we see programming smarts computers servers and lots of Boolean algebra in other words ones and zeros.

What a great start to the New Year look at this magic. PSD Energy leading the way in building Design and manufacture
20/01/2026

What a great start to the New Year look at this magic. PSD Energy leading the way in building Design and manufacture

As we prepare to wrap up for the year we carry out the essential maintenance to our fleet
19/12/2025

As we prepare to wrap up for the year we carry out the essential maintenance to our fleet

Big day for the PSD team today energising one BESS project into the 132kV connection substation, and then preping the 22...
09/12/2025

Big day for the PSD team today energising one BESS project into the 132kV connection substation, and then preping the 220kV transformer bay on the solar farm.

Great team work!!!!! We don’t need machines, with this team. Fantastic work team. Great achievement great milestones.

220kV Substation going together seamlessly great job from the team on site
05/12/2025

220kV Substation going together seamlessly great job from the team
on site

24/11/2025

All happening today on our latest BESS, the final layer of the bench getting laid. Great job from a great team.

Address

16 Williams Circuit, Pooraka
Adelaide, SA
5095

Opening Hours

Monday 8am - 5pm
Tuesday 8am - 5pm
Wednesday 8am - 5pm
Thursday 8am - 5pm
Friday 8am - 5pm

Telephone

+61882598100

Alerts

Be the first to know and let us send you an email when PSD Energy posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Share