06/01/2026
Phase 2 at Superior Wash is complete. 🧱💪
For this phase, the owner wanted us to skim coat several areas of the building to help create a more uniform look before the new coat of paint goes on.
Skim coating sounds simple from the outside, but when you’re working against old materials, old paint, existing coatings, new block, and patched areas — it becomes a process.
First, you have to grind and prep the old surfaces.
Then comes the bonding agent.
Then the first coat.
Then the rub down to even everything out.
Then the second coat to polish it up and get the wall ready for its final finish.
It takes patience. It takes detail. It takes care.
These walls are now cleaned up, strengthened, and ready to carry the legacy of Superior Wash into its next life cycle.
Next up — Phase 3: rebuilding the kiosk areas and restoring the trash enclosure.
Then on to the next.
Legacy Built. 🧱🔥