Hosting this year? Build what comes next by planning your kitchen project now.
The kitchen is often the center of holiday hosting, but a full remodel cannot be completed in a few weeks. A realistic timeline may include:
• 2–4 weeks for planning and design
• 4–8 weeks for permits, ordering, and material lead times
• 4–8 weeks for construction and final details
Starting in late September gives you time to identify repairs, confirm the scope, and determine what can realistically be completed before family arrives. Smaller updates may fit the calendar, while a full renovation may be better scheduled after the holidays.