06/07/2026
Scroll from the end to the beginning.
Bathroom remodel. Change out tubshower for a corner walk-in shower.
Subfloor was soft all the way thru. Replaced with new subfloor, moved shower drain and vent, replumbed with new shower handle and valves to shut off water to it. Replaced cpvc with pex and relocated pex run for shower handle. Leveled subfloor to keep edges looking good. Installed shower base, installed mold and mildew resistant drywall, mudded to level it all and repair other damaged drywall, primed with anti mildew paint. Installed shower walls, drain connections, shower valve trim, and caulked to prevent water leaks.
New floating floor installed with trim to cover edges. Reset toilet, water tested for leaks.
Second bathroom done.
Call Craig, he works in summer season too!