21/06/2026
A PRODUCTIVE -week on site end of week 2 . Stage 1 insulation PAR - Stage 2 insulation Superfoil - chipboard floor - Velux x 3 MK04 two number to main room , PK04 over stairwell - windows x 3 - electric first fix - plaster board to loft & stairwell.
All set for week 3- exterior roof complete & exterior complete - first fix plumbing - stair install - first floor general works ready for Plastering.