03/09/2026
Listed Building Consent: In late July 26 our clients received Full Planning and Listed Building Consent for their home in the Harleyford Conservation Area, Lambeth. We achieved consent in 15 weeks. There was no Pre-App, just straight in with a robust and comprehensive application addressing the items that required consent, including a whole house Air Source Heat Pump and fan coil heating system. We did grant 2No. EOT’s during the determination period, nearly doubling what should be a statutory determination period of 8 weeks but this approach appears still to be the fastest and cheapest route to a (positive) decision, listed building or not, over the last 2 years. I’ve been enjoying working with the clients on Stage 4 Technical Design now for items that need immediate attention, namely a new shower room, bathroom services at lower ground, whole house electrics and external joinery.