21/09/2026
Construction continues to advance at a strong pace across our Belgravia development, with significant progress made to both the structural framework and external envelope works.
The first and second floor structures are taking shape, with plywood decking laid to create the new floor platforms.
At ground floor level, new rear garden door openings have been successfully created, helping to enhance the connection between the internal living spaces and outdoor areas.
Externally, waterproofing and thermal performance works have progressed with the installation of membrane and insulation along the rear elevation. In tandem, construction has commenced on the new external brickwork wall running across the rear of the development, visibly transforming the site's appearance.
Masonry works continue to progress well, with blockwork construction advancing along the western party wall at first-floor level.
With structural, masonry and external envelope works all moving forward simultaneously, the Belgravia project is maintaining excellent momentum as the development continues to take shape.