09/10/2026
Been a busy old week this week!
WASHINGTON SITE
- Brickwork progressed to padstone height.
- 10x Steels delivered to site!
- Bifold lontel set in place ready for site survey.
- Garage floor insulated, drains for W/C amd utility set up, garage floor set.
- Garage walls cut out and removed, and padstones set to carry steels
- Steels set in rear amd side knockthrkughs to garage.
- Stud walls built to form W/C and utility
- Oak Staircase surveyed.
BIRTLEY SITE
- Floor Heights dropped to Block and Beam flooring requirements
- Underground drainage installed and inspected to carry rainwater.
- Trenchblock and brick work laid to Underside of Block and Beam floor height.
WASHINGTON SITE 2
- Boarding completed, and chases bonded to prep for plaster
- All walls and ceilings skimmed
- Cedar Fascias amd spffit delivery on site.
- Begun install of Cedar with this to finish next week.
To say the lads have grafted to bring all of this together this week is an understatement.
Oh and more merch arrive from workwear express too 😎
We go again monday 💪😎