Busy few weeks!
Started with an existing dwelling, added a new property pole and underground power, decommissioned the existing septic, demolished 3/4 of the house, dug in the new plumbing, and finally prepped and poured the additional footings and slab.
Thanks to the boys at Hyena Demolition , Flynnstone Plumbing, Hennig Electrical, and Balshaw Concrete Services for keeping it moving over the last few weeks.