CPE Construction were proud to be engaged by PowerNet (now Ventia) in 2025 to construct the new Control Room at the Shepparton Terminal Station.
Delivered within a live substation environment, this project presented unique challenges, including working safely beneath 220kV overhead powerlines, requiring careful planning, strict safety protocols, and close coordination across all teams.
This outcome reflects our capability in delivering complex infrastructure for critical network operations, with safety and quality at the forefront.
A big thank you to our trusted subcontractors Bell Earthmoving, Kialla Plumbing, CM Concreting, Bondpro, and all others involved. Your expertise and collaboration were essential in bringing this project to life.
We’re proud to contribute to infrastructure that supports the region’s energy network.