⚡ 11kV Generator Replacement: Final Push ⚡
Major progress on our 11kV backup generator replacement at a Gold Coast resort!
COMPLETED:
✅ Generator installed
✅ HV cable terminations
✅ NER installation
✅ Gen LV DB mounted
IN PROGRESS:
🔧 Protection Panel - relay wiring, VT & CT circuits
🔧 Control Panel - BMS integration
🔧 Final circuit terminations
THE REALITY:
Tight deadlines. High pressure. Non-negotiable timelines.
But when you’ve got quality HV subcontractors, suppliers, and testing partners who understand what’s at stake - you can pull off what seems impossible.
Massive shoutout to our QLD Power techs putting in big days away from home to get this critical infrastructure back online. 💪
Final stretch: commissioning and testing up next.